CONSTRUCTION OF THOMSON-EAST COAST LINE MAXWELL STATION –
CONSTRUCTION ACTIVITIES THAT WILL BE CARRYING OUT FOR THE 3RD QUARTER 2015
Hock Lian Seng Infrastructure will be conducting the following activities for the 3rd Quarter of 2015:
A) Silo Plant setting up
B) Recharge Well installation
C) Diaphragm Wall construction
D) Prelim Test Pile
E) ECM Setting up
F) Soil Investigation
It is inevitable that that some inconveniences such as noise, dust and traffic diversion may arise in the process of the above works. Please feel free to contact Hock Lian Seng Infrastructure Pte Ltd Public Relations Officer, Ms Alison Tee at 9137 2588, or Land Transport Authority Community Partnership Manager, Ms. Lim Ee Lee at 6295 7423 if you require further clarification or feedback.
|